Card Room Furnace Complete!
- Timothy L Higgins II
- Nov 29, 2016
- 1 min read
The second of the three furnaces planned for phase 1 is complete! The card room, Shrine room, and hall are now heated by the new card room furnace. People's Heating and Cooling has now finished 2 of the 3 furnaces planned for this fall at the temple. The last to be installed will be in the coat room and is scheduled to start right away. We have some core drilling and wall sawing to do to make way for the duct work on the North side. The furnace thermostats are now online and allow us to adjust the heat remotely when the temple is being used. The Foundation would like to thank Brent Drake and Peoples Heating and Cooling for their work and generous donations to this project!
Recent Posts
See AllStopped by the lodge today to check on furnace installs......Great News; the card room furnace is currently being installed! The unit and...
The MPF is proud to announce that the dining hall furnace is up and running! This is the first step in heating and cooling our building...